September 7 Main results of the day
The Ninth Arbitration Court of Appeal upheld the decision of the Moscow Arbitration Court to recover debt from a subcontractor under a construction contract in favor of the general contractor. The Court of Appeal agreed with the arguments of the lawyers of the Bureau of Lawyers “De jure” that under work contracts, the limitation period…