The Moscow Arbitration Court refused to satisfy the claims against the Principal of the lawyers of the Bureau of Lawyers “De jure” in the amount of more than 9 million rubles.
The Contractor, who had performed work under a construction contract demanded payment of a guarantee retention since he believed that the warranty periods for the work he performed had expired. During the consideration of the case, it was revealed that the Contractor had not fulfilled the warranty obligations, which entailed an extension of the warranty periods.
Agreeing with the above arguments, the court considered the claim brought by the opponents to be premature and refused to satisfy it in full. This case has already become the third successful example of judicial protection of the Principal from unreasonable demands of the contractor at this facility.
The interests of the Principal were represented by Yakov Prisyazhnyuk, Head of the Department for Economic Disputes.